Thursday, October 8, 2020

Construction Management-3

1 Scheduling of a project is affected by following things 
A Type of project
B Nature of activities
C Availability of resources 
D All of the Above
Answer: A

2 The WBS Structure is a ------ structure
A Triangle
B Matrix
C Square
D Tree
Answer: D

3 What is the principle to be used when deciding how many levels deep a Work Breakdown Structure (WBS) should be “broken down” to?
A  Use the WBS breakdown provided with the WBS template in the project management methodology.       that is the correct level for each task
B Break down all tasks and activities within the WBS to tasks of no more than 8 hours of duration so            that a task or activity will have a status update every day
C Break down tasks and activities in the WBS to the level at which the project core team will be                  managing and reporting on during project meetings.
D None of the above
Answer: D

4 A dummy activity
A Is artificially introduced
B Is represented by a dotted line
C Does not consume time
D All the above 
Answer: D

5 Work study consists of
A Effective use of plant and equipment
B Effective use of human effort
C Evaluation of human work
D All of the above
Answer: B

6 In process charts, the symbol used for inspection is
A Circle
B Square
C Arrow
D Triangle
Answer: B

7 Two hand process chart is commonly used for
A Repetitive operations
B Short operations
C Both ‘a’ and ‘b’
D None of the above
Answer: C

8 There are repetitive work cycles of short to long duration and wide variety of dissimilar work is performed is known as -------
A Time Study
B Motion Study
C Both of above
D None of the above
Answer: A

9 U.S Navy developed technique which is used to plan the construction of repetitive structural units is 
A ABC 
B LOB 
C both of the above
D None
Answer: B

10 The schedule is classified according to its use as
A Material ,Labour
B Equipment, Finance
C Both a and b
D None of the above
Answer: C

11 The WBS is depend upon the ------ and ------
A Shape and complexity
B Size and Complexity
C Level and Size
D None of the above 
Answer: B

12 What does a Work Breakdown Structure (WBS) “break down?”
A Project deliverables are broken down into tasks and activities
B The structural elements of the project facility and equipment are broken down for inventory and               tracking purposes
C Project costs are broken down into the departments where they are charged
D None of the above
Answer: A

13 A Milestone chart
A Shows the interdependencies of various jobs
B Depicts the delay of jobs, if any
C Points outgoing ahead of schedule of jobs, if any
D None of these.
Answer: D

14 The correct order of procedure in method study is
A Select – Record – Examine – Develop – Define – Install – Maintain
B Select – Define – Examine – Develop – Record – Install – Maintain
C Select – Record – Develop – Examine – Define – Install – Maintain
D Select – Record – Examine – Define – Develop – Install – Maintain
Answer: A

15 Which of the following is a scale plan?
A String diagram
B Flow process chart
C Operation process chart
D All of the above
Answer: A


for more updates and study material follow our site on top right corner 👉

No comments:

Post a Comment

Latest Published Blog

Geotechnical Engineering

Top Published Blogs