Thursday, October 8, 2020

Construction Management-1

1. Project performance consists of
A Time
B Cost
C Quality
D All of the above
Answer: D

2._______________ Manage the project by application of their knowledge, skill and experience at various stages.
A PMC
B ABC
C WBP
D MPI
Answer: A

3. When project is delay by cost or time then additional resources or time is required for completion of project is called
A PMC
B Schedule of PMC
C Project overrun
D Non of these.
Answer: C

4.------------- is the important sector that contributes majorly in economic growth of India
A Transport
B Health 
C Construction
D Education
Answer: C

5.Over all planning and control of project from inspection to completion aimed at meeting a client requirements in order to produce a functionally and financially viable project is  
A Planning
B Scheduling
C Optimizing resources
D Construction management
Answer: D

6. A report is present in depth techno commercial analysis carried out for the project idea for consideration of financial and other authorities empowered to take investment decision is
A Feasibility report
B Legal requirements
C Historical background
D None of these.
Answer: A

7.------------management is central to the any construction management
A Project
B Evaluation
D Analysis
D Work
Answer: A

8.The progress of ongoing project against the completed project and identification of key parameter which can play important role in project progress is 
A Project status
B Final product
C Project monitoring and reporting system
D None of these.
Answer: C

9. ______decides to undertake the work after detail analysis of the cost and the payment schedule for the project.
A Owner
B Consultant
C Contractor
D Client
Answer: A

10. _______is a group of person or person who gives the owner the technical advice for the project
A Owner
B Consultant
C Contractor
D Client
Answer: B

11. _____offers to do the job for a given sum of money and incase the tender is accepted his sign the contract with owner to undertake the construction.
A Owner
B Consultant
C Contractor
D Client
Answer: C

12. _________involves the purchase sale and development of land, residential and nonresidential building.
A) Real estate
B) Infrastructure sector
C) Geographical area
D) Non of these.
Answer: A

13. The project team is lead by __________Who is appointed by client and acts on his behalf.
A Contractor
B In charge
C Project manager
D None of these 
Answer: C

14. ______deals with the formulation and implementation of the corrective action necessary for achieving for project objectives.
A Cooperate level
B Forecasting status
C Control system
D None of these
Answer: C

15. The process combine with strategy and bland with become a tool more powerful than simply strategy and tactics is __________
A PMC Process
B Evolution and control process
C Strategy choice
D Non of these
Answer: A

for more updates and study material follow our site on top right corner 👉